Google–Kairos

Kairos Power is to build up to 500 of small reactors by 2035 and sell Google their output; the first, 50 MW Hermes 2 planned for 2030, sells to TVA, which passes Google its clean-energy attributes.

A deal between Google, Kairos Power

Why it matters

Google's agreement with Kairos Power sets milestones for repeated deployments of a new reactor design. The first plant is targeted for 2030, and the design has already changed once, from two small reactors to one of 50 . Google takes only that plant's clean-energy attributes through the Tennessee Valley Authority, which buys the electricity.

Tap a figure for the line in its source.

Kairos Power gives Google

  • from a fleet of Kairos plants by 2035, which are to sell Google energy, grid services and clean-energy attributes under PPAs; the first, Hermes 2, sells its power to TVA instead (below)
  • the clean-energy attributes of the first plant, Hermes 2 (50 , targeted for 2030), through TVA, which buys the electricity itself

Google gives Kairos Power

  • payments under the plants' PPAs with Google, at prices no party discloses (TVA, not Google, buys Hermes 2's power)

Oct 14, 2024 announced by Kairos Power and Googleupdated Nov 19, 2026Hermes 2 under construction disclosed by the parties

What happened

Google signed an agreement with Kairos Power to buy nuclear power. Google calls it the world's first corporate agreement to buy power from a fleet of small modular reactors. Kairos Power is to build and run plants totaling up to 500 by 2035 and sell their output to Google. The deal sets milestones. The first plant, the 50 MW Hermes 2 in Oak Ridge, Tennessee, broke ground in April 2026 and is targeted for 2030. The plant is to sell its electricity to the Tennessee Valley Authority instead of Google. The authority's grid serves Google's Tennessee and Alabama data centers. Google gets the plant's clean-energy attributes, the rights to claim its clean-energy benefits, through the Tennessee Valley Authority. Kairos Power says the first six of its 75 MW commercial reactors (450 MW) are to be delivered under the agreement by 2035. No price has been disclosed.

Sources 14 documents — 9 company releases · 2 other documents · 1 SEC filing · 1 regulatory filing · 1 press report

Research trail Found 348 documents and read 319 of them while checking this deal and related ones.

  1. Kairos Power · company releasekairospower.com
    States 500 MW mpda
  2. Kairos Power · company releasekairospower.com
    States 450 MW fleet plan
  3. SEC filingsec.gov
    States up to 50 MW hermes2 PPA
  4. Kairos Power · company releasekairospower.com
    States 50 MW hermes2 design
  5. Kairos Power · company releasekairospower.com
    States groundbreaking
  6. company releaseblog.google
    Cited by the record; no single figure is quoted from it.
  7. company releaseblog.google
    Cited by the record; no single figure is quoted from it.
  8. regulatory filingnrc.gov
    Cited by the record; no single figure is quoted from it.
  9. company releasekairospower.com
    Cited by the record; no single figure is quoted from it.
  10. company releasekairospower.com
    Cited by the record; no single figure is quoted from it.
  11. company releasekairospower.com
    Cited by the record; no single figure is quoted from it.
  12. other documenttvppa.com
    Cited by the record; no single figure is quoted from it.
  13. press reportSep 21, 2026techcrunch.com
    Cited by the record; no single figure is quoted from it.
  14. other documentans.org
    Cited by the record; no single figure is quoted from it.

The record's own summary of its sourcing: Kairos + Google releases (Oct 14 2024; Aug 18 2025) + TVA FY2025 10-K + NRC CLI-24-03 + Kairos (Apr 2026 groundbreaking; fleet page) + TVPPA Magazine (Jul 2026) + TechCrunch and ANS (Sep 2026) · as of Oct 2026

The evidence 5 sourced figures · 2 disputes

The record's headline Google–Kairos: up to 500 of small reactors by 2035; the first, Hermes 2, sells to TVA

Size
up to 500 MW by 2035
When
Oct 2024 (master agreement) → Aug 2025 (Hermes 2 / TVA PPA) → Apr 2026 (ground broken) → 2030 (first power, target)
Status
Hermes 2 under construction (ground broken Apr 2026) → first power 2030 (target)
Structure
Master Plant Development Agreement (Oct 2024): Kairos to sell the plants' output to Google under PPAs; the first plant, Hermes 2, sells to TVA under its own PPA, Google taking the attributes
Programme
Time-to-power
Parties
Google anchor offtaker (under PPAs; Hermes 2's attributes via TVA) · Kairos Power smr-developer + builder-operator
Record
disclosed / primary source · as of Oct 2026

Resolved figures 5 each with the verbatim line from its document

  • mpda500 MW
    a Master Plant Development Agreement (Oct 14 2024): Kairos 'will develop, construct, and operate' plants totaling 500 MW by 2035 and sell Google 'energy, ancillary services, and environmental attributes' under 'Power Purchase Agreements (PPAs)', the first deployment by 2030, with 'milestone-based accountability' built in. Google calls it 'the world’s first corporate agreement to purchase nuclear energy from multiple small modular reactors' and says 'up to 500 MW'. 'a power purchase agreement with Google for up to 500 MWe' (OECD-NEA) and 'an MoU' (WNISR) are outside labels. Whether it obliges Google to take all 500 MW neither company says in terms: Google declined to tell Latitude Media 'whether the company has signed an official power purchase agreement or something more along the lines of a memorandum of understanding', its spokesperson saying the agreement 'defines performance milestones and a pricing model' while 'nothing is guaranteed' (Oct 2024). Tyler Mauldin, a lead on Google's energy markets and policy team, has since called it an 'agreement in 2024 to purchase 500 MW of nuclear energy', without the 'up to' of Google's announcement (TVPPA Magazine, Jul 23 2026). The Nuclear Innovation Alliance, naming this agreement as its example, calls such contracts 'not firm PPAs per se, but are explicit precursors to PPAs, subject to further steps in project development' (Oct 2025)
    “Kairos Power and Google have signed a Master Plant Development Agreement, creating a path to deploy a U.S. fleet of advanced nuclear power projects totaling 500 MW by 2035.”
    Kairos release (Oct 14 2024) · kairospower.com
  • fleet-plan450 MW
    75 MWe commercial reactors, sited in pairs, the 'First 6 reactors (450 MWe)' by 2035 under the Google agreement — Kairos's own pages. With Hermes 2's 50 MWe, that is the 500 MW (the record's addition: 50 + 450; the Aug-2025 release calls Hermes 2 'the first deployment under Kairos Power’s landmark deal with Google'). Kairos's technology page gives '150 MWe [2 x 75 MWe]' for the dual-unit 'Minimum configuration' and six reactors, 450 MWe, for its 'Standard configuration'. No primary on file gives the unit size, which remains disputed among outside readings — WNISR's '70-MW SMRs', which does not match; OECD-NEA's '320 MWth (75 MWe)', which does; and DCD's 'six to seven reactors' (Oct 2024), which fits Hermes 2 plus six
    “Scalable deployment of 75 MWe commercial reactors, sited in pairs. First 6 reactors (450 MWe) to be delivered by 2035 under a long-term, multi-plant agreement with Google.”
    Kairos 'Iterative Development' page (undated; read Oct 2026) · kairospower.com
  • hermes2-ppaup to 50 MW
    TVA buys up to 50 MW of Hermes 2's electricity under a 2025 PPA, 'anticipated to come online as early as 2030' — the first US utility PPA for a Gen IV reactor (Kairos/TVA/Google, Aug 18 2025). Google does not buy these electrons: it 'will receive the clean energy attributes from the plant through the TVA system' for its data centers in Montgomery County, Tennessee and Jackson County, Alabama. TVA's 10-K is the buyer's own disclosure. No price figure is given anywhere: per POWER (Aug 18 2025), TVA confirmed only that it will pay 'market-based prices that are fixed based on time-of-day' for the plant's electricity
    “In 2025, TVA signed a PPA to purchase up to 50 MW of electricity from the Kairos Power Hermes 2 Plant in Oak Ridge, Tennessee. The capacity is anticipated to come online as early as 2030.”
    TVA FY2025 10-K · sec.gov
  • hermes2-design50 MW
    one 50 MW reactor, enlarged from the original two-unit plan to speed delivery to Google, scheduled to begin operations in 2030; Kairos now calls it a '50 MWe commercial-scale reactor'. What the two-unit original was rated at is contested (see early-design); the NRC's 2024 construction permits were for that two-unit plant
    “To accelerate the delivery of clean energy to Google, Kairos Power will increase Hermes 2’s output from 28 MW to 50 MW generated by a single reactor, scheduled to begin operations in 2030.”
    Kairos/TVA/Google release (Aug 18 2025) · kairospower.com
  • groundbreaking2026
    ground broken on Hermes 2 at Oak Ridge on Apr 17 2026 — Kairos's 'first commercial-scale reactor' and the first power-producing Gen IV reactor to hold an NRC construction permit
    “April 17, 2026 OAK RIDGE, Tenn. – Today, Kairos Power broke ground on the Hermes 2 Demonstration Plant in Oak Ridge, Tenn. – the company’s first commercial-scale reactor and the first-ever power-producing Gen IV reactor to receive a construction permit from the Nuclear Regulatory Commission (NRC).”
    Kairos release (Apr 17 2026) · kairospower.com

Contested figures 2 not reconciled — every position side by side, with its source and tier

early-designone entry, in its own words
20 MWe — 'a combined electrical power output of 20 megawatts electric' from two 35 MWt units (the Commission's 2024 order authorizing the construction permits, CLI-24-03) vs 28 MW — two '14 MWe reactors' in 'the original dual-unit plant concept' (Kairos's newsletter; the Aug-2025 release raises output 'from 28 MW to 50 MW'). No document reconciles the two; it matters only as the baseline the 50 MW redesign departs from NRC CLI-24-03 vs Kairos release + newsletter
first-powerone entry, in its own words
2030 — Kairos, TVA and Google ('scheduled to begin operations in 2030'; TVA's 10-K: 'as early as 2030'); restated in Sep 2026, the day before Samsung C&T's release, when TechCrunch reported that Kairos 'expects Hermes 2 to begin operating in 2030, in line with its original agreement with Google' (Sep 21 2026) vs 2031 — Samsung C&T's Korean release (Sep 22 2026) says the 'Hermes' demonstration reactor Kairos is building targets operation in 2031, naming no unit. It describes that reactor as the first non-light-water reactor in more than 50 years to win NRC construction approval, which Kairos says of the 2023 permit for Hermes 1, the non-power test reactor; but the same release has Samsung joining that reactor's design and constructability review, and Kairos's own release of the deal puts Samsung's investment into Hermes 2. So the release does not settle which unit the 2031 is for, and neither unit's published year is 2031: of Hermes 1, ANS reported two days later that Kairos 'is aiming to have Hermes on line in 2028' (Sep 24 2026) Kairos/TVA/Google + TVA 10-K + TechCrunch (Sep 21 2026) vs Samsung C&T release; ANS (Sep 24 2026)

Scope note what this record leaves to other records

Not this deal: Hermes 1, the non-power test reactor beside Hermes 2 (Kairos: its 2023 permit was 'the first U.S. construction permit for a non-water-cooled reactor to be issued in over 50 years'); Samsung C&T's Sep-2026 agreement to help fund and build Hermes 2 (kairos entity note); Google's other nuclear bets — NextEra's Duane Arnold restart (pw-goog-duane-arnold), Elementl's three sites, Constellation's uprates (pw-goog-constellation).

More between Google and Kairos Power

The record holds no other deal between them.