Why it matters
GE Vernova sells places in its gas-turbine queue before customers order. Reservations drove the queue from 50 to 116 in five quarters against ~15 GW a year of output. The total reached 122 GW the next quarter, and reservations fell for the first time in the series as 13 GW became orders and 8 GW of new holds came in.
What happened
GE Vernova, the biggest Western maker of large gas turbines, has 122 gigawatts spoken for. That includes 64 gigawatts of firm orders and 58 gigawatts of slot reservation agreements. The customer pays a deposit of roughly a fifth to a quarter of the turbine's price just to hold a factory slot, before it has even picked a site. The combined total went from 50 to 122 gigawatts in six quarters. Until the latest quarter, reservations grew faster, from 21 to 63 gigawatts, against 29 to 53 for firm orders. In the latest quarter, 13 gigawatts of reservations became firm orders, after 6 and 10 in the two quarters before. That was more than the 8 gigawatts of new reservations signed. As a result, reservations fell to 58 and firm orders rose to 64. GE Vernova shipped about 15 gigawatts of turbines in 2025 and 12.8 in the first nine months of 2026. It is pushing toward 20 a year, then 24, then 30. Given those volumes, GE Vernova told investors it is sold out of new equipment through 2028 and expects to be largely sold out for 2030 by the end of 2026. On its April call, GE Vernova said roughly one turbine in five under contract was explicitly for a data center. The other four were for what it calls 'traditional' customers, such as utilities and independent power producers. The only confirmed reservation price comes from one public filing. The filing gives a price of $25 million for a Kentucky utility to hold a single 2030 slot. Of the two later reports that repeat the figure, one cites the filing. The other describes the price as if an anonymous developer were paying it.
Sources 24 documents — 10 SEC filings · 6 transcripts · 5 company releases · 2 press reports · 1 regulatory filing
Research trail Found 321 documents and read 311 of them while checking this deal and related ones.
- States 3 figures: 122 GW combined queue series · 13 GW Q3 2026 mechanics · at least 130 GW ye target trajectory
- States 3 figures: SRA conversion time · 20% SRA deposit · SRA price premium
- States 3 figures: $19.5B down payments · 12.8 GW shipments 9m 2026 · 36.7 GW orders 9m 2026
- States 2 figures: 63 GW backlog vs SRA split · 30 GW capacity ladder
- States 2 figures: 15.3 GW shipments series · 29.8 GW orders series
- States 21 GW Q4 2025 mechanics
- States 100 GW Q1 2026 step
- States 19 GW Q1 2026 mechanics
- States 63 GW turn forecast
- States 55 GW combined queue 2q25
- States 21 GW SRA definition
- States SRA classification
- States 10 GW sold out
- States 20% data center share
- States $25M slot reservation fee
- States 3.6 GW counterparty nrg
- States $1.3B US manufacturing investment
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
The record's own summary of its sourcing: GEV quarterly releases 1Q25–3Q26 (8-K ex-99.1) + FY25 10-K KPIs + 2Q26 and 3Q26 10-Qs + investor-update deck/transcript 12/9/2025 + 3Q25 / 4Q25 / Q1'26 / 2Q26 call transcripts + BofA conference 3/18/2026; Kentucky PSC order 2025-00045; NRG FY25 10-K; Utility Dive 12/2025 + 7/2026 (updated: 3Q26 release + 10-Q, 10/28/2026) · as of Oct 2026
The evidence 25 sourced figures · 4 disputes
The record's headline GE Vernova turbine slots: backlog + reservations 83 → 100 → 116 → 122 ; new equipment sold out through 2028
- Size
- 122 GW under contract at 3Q26 (64 GW backlog + 58 GW slot reservations); ≥130 GW guided for YE2026
- When
- Apr 2026 (83 → 100 GW) → Jul 2026 (116 GW) → Oct 2026 (122 GW)
- Status
- operational — series through 3Q26 (Oct 28 2026); new equipment sold out through 2028; backlog again above reservations at 3Q26 (64 vs 58 GW), the turn the 2Q26 call (Jul 22 2026) forecast for the second half of 2026
- Structure
- slot-reservation agreements (20–25% deposit holds a delivery slot; converts to an equipment order once site + EPC are set, gas supply is clear and permitting is progressing — 'more our classification than the customers', CEO 10/2025 — in '6 to 18 months today', CEO 3/2026) ahead of firm backlog
- Programme
- Time-to-power
- Parties
- GE Vernova turbine-maker; sells the factory slot before the order
- Record
- disclosed / primary source · as of Oct 2026
Resolved figures 25 each with the verbatim line from its document
- combined-queue-series122 GW122 GW at 3Q26 — ONE time series, each step stated in that quarter's release: 50 (1Q25) → 55 (2Q25) → 62 (3Q25) → 83 (4Q25) → 100 (1Q26) → 116 (2Q26) → 122 (3Q26). The documents' other numbers here are not rival answers to one question: 56 and 63 are the reservation halves at 1Q26 and 2Q26, 54 is IEEFA's sum of rounded 2Q25 halves (combined-queue-2q25), and 60, 80, 110 and 125 are year-end targets (ye-target-trajectory). 'Gas equipment under contract' in GEV's usage = backlog + slot reservation agreements, never backlog alone
“Gas Power equipment backlog and slot reservation agreements grew from 116 to 122 GW; now anticipate reaching at least 130 GW by year-end 2026”
GEV 3Q'26 8-K ex-99.1 (10/28/2026) · sec.gov - q4-2025-mechanics21 GWhow 62 became 83 in 4Q25: 24 GW of new gas equipment contracts signed, 21 GW of them slot reservations and 3 GW orders; 8 GW of earlier reservations converted to orders; 3 GW shipped. Backlog 33 → 40 GW, reservations 29 → 43 GW. The release gives whole GW, and its figures do not quite close on either side: backlog 33 + 3 + 8 − 3 = 41 GW against the 40 it states, and reservations 29 + 21 − 8 = 42 GW against the 43 it states (the monitor's arithmetic; the release does not reconcile them)
“In the fourth quarter, signed 24 gigawatts (GW) of new gas equipment contracts including 21 GW of slot reservation agreements and 3 GW of orders. Converted 8 GW of existing slot reservation agreements to orders and shipped 3 GW of equipment; resulting in backlog growth from 33 to 40 GW and an increase in slot reservation agreements from 29 to 43 GW.”
GEV 4Q'25 8-K ex-99.1, Power segment · sec.gov - q1-2026-step100 GWthe jump this record began with: +17 GW in one quarter, to 100 GW — the record's original figure and citation (gevernova.com copy of the Q1'26 release). The same release lifted the year-end target to 'at least 110 GW'; three months later it was 'at least 125' (see ye-target-trajectory)
“Gas Power equipment backlog and slot reservation agreements grew from 83 to 100 GW; now anticipate reaching at least 110 GW by year-end 2026”
GEV Q1'26 release (gevernova.com, 4/22/2026) · gevernova.com - q1-2026-mechanics19 GWhow 83 became 100: 21 GW of new gas contracts signed, 19 of them slot reservations and only 2 firm orders — reservations, not orders, are nine-tenths of the surge; 6 GW of earlier reservations converted to orders; 4 GW shipped. Backlog 40 → 44 GW, reservations 43 → 56 GW
“Signed 21 gigawatts (GW) of new gas equipment contracts, including 19 GW of slot reservation agreements and 2 GW of orders. Converted 6 GW of existing slot reservation agreements to orders and shipped 4 GW of equipment; resulting in backlog growth from 40 to 44 GW and an increase in slot reservation agreements from 43 to 56 GW.”
GEV 1Q'26 8-K ex-99.1, Power segment · sec.gov - backlog-vs-sra-split63 GWthe split, quarter by quarter (backlog + reservations = combined): 1Q25 29 + 21 = 50 · 2Q25 29 + 25 (rounded components; the release states 55) · 4Q25 40 + 43 = 83 · 1Q26 44 + 56 = 100 · 2Q26 53 + 63 = 116 · 3Q26 64 + 58 = 122 (this entry's figure and quote are the 2Q26 step; 3Q26's is q3-2026-mechanics). Reservations exceeded firm backlog from 4Q25 through 2Q26, and at 3Q26 backlog is the larger half again; reservations are NOT inside backlog — a record that adds a 'backlog' figure to a 'backlog + SRA' figure double-counts. 2Q26 signed 20 GW (18 GW reservations + 2 GW orders), converted 10, shipped 3
“Signed 20 gigawatts (GW) of new gas equipment contracts, including 18 GW of slot reservation agreements and 2 GW of orders. Converted 10 GW of existing slot reservation agreements to orders and shipped 3 GW of equipment; resulting in backlog growth from 44 to 53 GW and an increase in slot reservation agreements from 56 to 63 GW.”
GEV 2Q'26 8-K ex-99.1, Power segment · sec.gov - q3-2026-mechanics13 GWhow 116 became 122, and the turn: 11 GW of new gas equipment contracts signed in 3Q26 — 8 GW of reservations and 3 GW of orders — while 13 GW of earlier reservations converted to orders and 5 GW shipped. Backlog 53 → 64 GW; reservations 63 → 58 GW. It is the first quarter the reservation total fell in the record's series (21 → 25 → 29 → 43 → 56 → 63 → 58): conversions (13 GW) outran new reservations (8 GW), and backlog is again the larger half, as it was before 4Q25. GE Vernova had forecast the turn a quarter earlier (turn-forecast)
“Signed 11 gigawatts (GW) of new gas equipment contracts, including 8 GW of slot reservation agreements and 3 GW of orders. Converted 13 GW of existing slot reservation agreements to orders and shipped 5 GW of equipment; resulting in backlog growth from 53 to 64 GW and a decrease in slot reservation agreements from 63 to 58 GW.”
GEV 3Q'26 8-K ex-99.1, Power segment · sec.gov - turn-forecast63 GWthe turn, forecast a quarter ahead: with 63 GW of reservations against 53 GW of backlog at 2Q26, the CEO said on the 2Q26 call (Jul 22 2026) that in the second half of 2026 GE Vernova expected 'to convert many of these SRAs into orders', 'achieving an important inflection point with gigawatts and backlog greater than SRAs'. At 3Q26 backlog was 64 GW against 58 GW of reservations (q3-2026-mechanics)
“Backlog grew from 44 to 53 gigawatts, and SRAs increased from 56 to 63 gigawatts. For our total gigawatts under contract, demand remains diverse with approximately 100 customers in 26 different countries, of which approximately 80% are traditional customers and 20% are for data centers. We now expect at least 125 gigawatts under contract by the end of the year. We had a strong first half and now have agreements signed into ’31. In the second half of the year, we expect to convert many of these SRAs into orders, driving continued growth in our backlog while achieving an important inflection point with gigawatts and backlog greater than SRAs.”
GEV 2Q'26 earnings call transcript (7/22/2026), CEO · gevernova.com - combined-queue-2q2555 GW55 GW at 2Q25 — this record follows the release over IEEFA's '54GW in the second quarter of 2025': IEEFA's own footnote cites this release, and 54 is the sum of the deck's rounded components (29 + 25). A tier-2 number that disagrees with the tier-1 primary it cites cannot outrank it
“Gas Power equipment backlog and slot reservation agreements grew from 50 to 55 GW”
GEV 2Q'25 8-K ex-99.1 (7/23/2025) · sec.gov - sra-definition21 GWwhat a slot reservation agreement is, in GEV's own words: gigawatts 'not yet in backlog'. The customer has paid a deposit and secured a delivery slot but has not chosen a site or signed its EPC contract, so GEV does not record it as an order ('until they've chosen the site and we're working with the EPC on building the plant, we don't record it in our backlog' — CEO, BofA conference 3/18/2026, the transcript sra-deposit cites). How long that takes: sra-conversion-time; whose line it is: sra-classification. The 21 GW of 1Q25 was 63 GW by 2Q26 and 58 GW at 3Q26, once 13 GW had converted to orders
“29 gigawatts of Gas Power equipment in backlog, with 21 gigawatts of slot reservation agreements not yet in backlog”
GEV Q1'25 release (gevernova.com, 4/23/2025) · gevernova.com - sra-conversion-time6 monthshow long a reservation takes to become an order, by GEV's CEO: 'I would say 6 to 18 months today' (asked whether it was '9 to 12 months usually'), 'maybe extending a little bit' because customers now reserving slots into 2031 are 'still working through their EPC fuel and other dynamics like that'. A range he gave, not a term of the agreements
“I would say 6 to 18 months today. And the reason I would say it's maybe extending a little bit is because as people now are starting to secure slot reservation agreements into even ‘31, by default, it's going to take a little bit longer before they convert to order because they're still working through their EPC fuel and other dynamics like that.”
GEV CEO at BofA Global Industrials conference (3/18/2026), transcript · gevernova.com - sra-classificationwhere a reservation ends and an order begins is GEV's own line, by its CEO on the 3Q25 call (Oct 22 2025): it waits for the customer's EPC contracts, 'transparency on their gas availability' and progress on permitting before booking an order, and 'the orders classification to be candid is more our classification than the customers', since in many cases customers provide 'enough financial capital on day one that one could argue we could be booking these things as orders'. The CFO added on the same call that in both reservations and orders 'there's a measurable amount of cash funding upfront and down payments. And in both cases, they're non-refundable'
“Now we don't want to put things into backlog until the customers to secure their EPC contracts until we have transparency on their gas availability until the permitting process is progressing. So, the orders classification to be candid is more our classification than the customers, right? Because in many cases, they're providing us enough financial capital on day one that one could argue we could be booking these things as orders.”
GEV 3Q'25 earnings call transcript (10/22/2025), CEO and CFO · gevernova.com - sra-deposit20%the CoWoS-allocation mechanic, stated by the seller: customers 'have often put down 20% to 25% of the gas turbine contract in deposit' to hold the slot ('directionally 20% of those contracts paid for today' on the Apr-2025 call). Cash before order — see down-payments for the balance-sheet trace
“So these are cases where customers have often put down 20% to 25% of the gas turbine contract in deposit and have secured the slot, but they haven't necessarily yet secured their EPC contracts.”
GEV CEO at BofA Global Industrials conference (3/18/2026), transcript · gevernova.com - sra-price-premium10reservations are priced '10 to 20 points' above what is already in backlog (CEO, BofA 3/2026; the same '10 to 20 points of pricing strength' on the 4Q25 call) — GEV's only public statement of its own turbine pricing, and it is relative. The absolute $/kW stays contested (see turbine-price-per-kw)
“the slot reservation agreements are on average 10 to 20 points higher in price than what's already in backlog”
GEV CEO at BofA Global Industrials conference (3/18/2026), transcript · gevernova.com - down-payments$19.5Bthe deposits show up as cash: a $19.5B nine-month inflow from contract liabilities and current deferred income in 9M26, 'driven by down payments on orders and slot reservation agreements at Power, and down payments at Electrification' — against $2.4B in the same period of 2025 (same filing), and up from $13.7B at the half-year (2Q26 10-Q). On the balance sheet, Power's 'Equipment and other service agreement liabilities' grew from $14,550M at Dec 31 2025 to $31,173M at Sep 30 2026 (Note 9, which says contract liabilities 'primarily represent cash received from customers under ordinary commercial payment terms in advance of delivery of equipment orders or servicing of customers’ installed base'). Customers are financing the turbine ramp before a single one of these units ships
“The cash inflow from changes in working capital was primarily driven by: contract liabilities and current deferred income of $19.5 billion, driven by down payments on orders and slot reservation agreements at Power, and down payments at Electrification”
GEV 3Q'26 10-Q, MD&A liquidity (EDGAR) · sec.gov - ye-target-trajectoryat least 130 GWguidance has been beaten every time it was set: YE2025 'at least 60 GW' (Jul 2025 call) → 'approximately 80GW' (Dec 9 2025 investor update) → actual 83 ('we were talking in the middle of last year at 60GW and landed at 83GW', 4Q25 call); YE2026 'at least 110 GW' (Apr 2026) → 'at least 125 GW' (Jul 2026) → 'at least 130 GW' (Oct 2026, with 122 GW already under contract at 3Q26 — the year is still open). BNP's Sutton says the market is looking for 130–140 GW (Utility Dive, on the 2Q26 print) — a sell-side expectation, not guidance; the October guide's floor now equals the low end of it
“We now expect our backlog to exceed $200 billion in the fourth quarter, with improved margins, and to exit 2026 with at least 130 GW of gas equipment under contract.”
GEV 3Q'26 8-K ex-99.1, CEO statement · sec.gov - capacity-ladder30 GWthree rungs of one ladder, not rival estimates: ~20 GW/yr annualized output from 3Q26 ('over 280 new machines' installed, Q1'26 call) → 24 GW in 2028 → 30 GW in 2030, from the existing Greenville and Belfort footprints. Against 122 GW under contract at 3Q26 that is still about four to five years of output at 24–30 GW a year — the arithmetic behind 'sold out'
“To meet this demand, we remain on track to deliver 20 GW of annual gas turbine output in the third quarter of 2026, with 24 GW in 2028, and we are implementing actions to produce 30 GW in 2030.”
GEV 2Q'26 8-K ex-99.1, CEO statement · sec.gov - shipments-series15.3 GWwhat actually shipped, from the 10-K KPI table: 13.8 GW (2023) → 11.9 (2024) → 15.3 (2025); 4 GW in 1Q26, 3 GW in 2Q26 and 5 GW in 3Q26 (the releases' whole-GW roundings — see shipments-9m-2026). Shipments in 2023–2025 were not ~10 GW a year: the lowest of those years was 11.9 GW (2024), and the 20 GW/yr figure is a mid-2026 run-rate target that neither 3Q26 filing restates
“Sales in units 2025 2024 2023 Gas Turbines 81 75 91 Heavy-Duty Gas Turbines 54 48 58 HA-Turbines 24 15 14 Aeroderivatives 27 27 33 Gas Turbine Gigawatts 15.3 11.9 13.8”
GEV FY2025 10-K, Power KPIs (sales) · sec.gov - shipments-9m-202612.8 GWwhat shipped in 2026 so far, from the same KPI row in the 10-Qs: 4.2 GW in 1Q26, 3.3 in 2Q26 and 5.3 in 3Q26 — 12.8 GW over the nine months, against 12.2 GW in the nine months of 2025 (3Q25: 4.0). The releases' 'shipped 4 GW', '3 GW' and '5 GW' match these quarters at whole-GW rounding (they sum to 12, not 12.8). Nine months of shipments, so not the 20 GW/yr run-rate that capacity-ladder names as a target from 3Q26
“Three months ended September 30 Nine months ended September 30 Sales in units 2026 2025 2026 2025 Gas Turbines 32 20 86 60 Heavy-Duty Gas Turbines 19 14 47 44 HA-Turbines 7 6 15 19 Aeroderivatives 13 6 39 16 Gas Turbine Gigawatts 5.3 4.0 12.8 12.2”
GEV 3Q'26 10-Q, Power KPIs (sales) · sec.gov - orders-series29.8 GWfirm orders in GW (reservations excluded): 9.5 (2023) → 20.2 (2024) → 29.8 (2025), 3x in two years; HA-class units 8 → 25 → 43. Orders ran roughly 2x shipments in both 2024 and 2025, and reservations grew faster still — 4Q25 alone: backlog 33 → 40 GW, reservations 29 → 43 GW (q4-2025-mechanics). 2026 is already past all of 2025 after nine months (orders-9m-2026)
“Orders in units 2025 2024 2023 Gas Turbines 173 112 93 Heavy-Duty Gas Turbines 110 68 41 HA-Turbines 43 25 8 Aeroderivatives 63 44 52 Gas Turbine Gigawatts 29.8 20.2 9.5”
GEV FY2025 10-K, Power KPIs (orders) · sec.gov - orders-9m-202636.7 GWfirm orders in GW, the same KPI row for 2026: 16.6 GW in 3Q26 (7.4 in 3Q25) and 36.7 GW over the nine months (19.6) — already more than all of 2025's 29.8, and 2.9x the 12.8 GW shipped in the same months (the monitor's division). 3Q26 alone: 55 heavy-duty units, 21 of them HA-class, and 57 aeroderivatives. The 16.6 matches the release's 3 GW of new orders plus 13 GW of reservations converted, at whole-GW rounding — the monitor's reading of why orders jumped in the quarter reservations fell
“Three months ended September 30 Nine months ended September 30 Orders in units 2026 2025 2026 2025 Gas Turbines 112 29 262 114 Heavy-Duty Gas Turbines 55 20 135 69 HA-Turbines 21 13 48 28 Aeroderivatives 57 9 127 45 Gas Turbine Gigawatts 16.6 7.4 36.7 19.6”
GEV 3Q'26 10-Q, Power KPIs (orders) · sec.gov - sold-out10 GW'sold out' is GEV's own word: new equipment sold out through 2028 and under 10 GW of 2029 delivery slots left going into 2026 (deck), and the CEO 'would expect to be largely sold out of deliveries in 2030 by the end of 2026' (same-day transcript). The record's earlier 'sold out through 2030' compressed the two statements; the 2030 claim is an expectation for end-2026. At BofA in March the 'sold out through '28 and expect to be sold out through 2030 by year-end '26' framing was the analyst's question, not a GEV restatement; the CEO's own words there were 'if you can't get a new heavy duty gas turbine until '29, which is our reality today'
“Now sold out on new equipment through ‘28 … less than 10 GW left to sell for ‘29”
GEV investor update deck (12/9/2025), p.6 · gevernova.com - data-center-share20%~20% of the 100 GW under contract at 1Q26 'explicitly supporting data centers' (~20 GW); the share was 'fairly negligible' in the 29 GW backlog of 1Q25 (CEO, 1Q25 call 4/23/2025); at Dec 2025 the CEO put hyperscalers — a subset of data-center buyers, not the whole category — at 'only 10%' of backlog (investor-update Q&A). Backlog and reservations carry different shares: at BofA (3/18/2026) the CEO put data centers at '10% to 15%' of the ~40 GW backlog but 'about a third' of slot reservation agreements. The 80/20 split was repeated at 2Q26 across ~100 customers in 26 countries (Utility Dive). Data centers are the marginal buyer, not the majority buyer — GEV's 'traditional customers' are. GEV never narrows that category; Utility Dive glosses it as 'traditional customers like utilities', and the record's own named reservers span a utility (LG&E/KU) and an IPP (NRG)
“Approximately 80% of our total gigawatts under contract are with traditional customers, with the remaining 20% explicitly supporting data centers.”
GEV Q1'26 earnings call transcript (4/22/2026), CEO · gevernova.com - slot-reservation-fee$25Mthe one hard price on a slot: LG&E/KU paid $25M under a Unit Reservation Agreement to reserve a manufacturing slot for Brown 12 (commercial operation 2030) 'and to lock in firm pricing for the equipment'. ONE contract in one public filing: GridLab (Sep 2025) cites the CPCN filing by name, IEEFA (Oct 2025) cites GridLab while re-describing it as 'one developer reporting that they paid GE Vernova USD25 million' — the apparent three-way corroboration is one source. The order does not call the fee non-refundable; that word is IEEFA's. A data point about one contract, not a market rate
“LG&E/KU explained that, under this agreement, LG&E/KU agreed to pay $25 million to GE to reserve a “manufacturing slot” in GE’s manufacturing process so that the Brown 12 equipment will be manufactured and delivered in time for commercial operation in 2030 and to lock in firm pricing for the equipment.”
Kentucky PSC order, case 2025-00045 (10/28/2025) · psc.ky.gov - counterparty-nrg3.6 GWa reservation seen from the buyer's side, the record's one independent cross-check on the seller's series: NRG's slot reservations with GEV grew 1.2 GW of 7HA (FY24 10-K) → 3.6 GW (FY25), under a development agreement with GEV and Kiewit's TIC for up to 5.4 GW of combined-cycle projects; first projects by end-2029. Other named reservers on file: LG&E/KU (Brown 12, above) and Blue Energy (two 7HA.02 for 2029 delivery, May-2026 joint release). The rest of the 122 GW under contract at 3Q26 is unnamed
“Additionally, NRG has entered into slot reservation agreements with GEV for the procurement of 3.6 GW of 7HA gas turbines.”
NRG FY2025 10-K (MD&A) · sec.gov - us-manufacturing-investment$1.3Bthe supply response, company-stated: nearly $1.3B across U.S. plants and research centers, 2025–2028. The Jan-2025 'nearly $600M over two years / 1,500 jobs' is the first tranche inside it (the Charleroi release says it 'builds on' that January commitment), not a rival total; IEEFA's 'USD720 million' has no primary — its footnote points at a $41M Schenectady release. Note the scale: ~$1.3B of capex over four years against a $19.5B nine-month cash inflow from contract liabilities and current deferred income, which the 10-Q says was driven by down payments (down-payments; Power and Electrification together)
“The Charleroi expansion is part of GE Vernova's broader plan to invest nearly $1.3 billion across its U.S. manufacturing facilities and research centers between 2025 and 2028 to strengthen domestic manufacturing capacity, accelerate innovation, and help meet growing electricity demand.”
GEV Charleroi expansion release (gevernova.com, 7/30/2026) · gevernova.com
Contested figures 4 not reconciled — every position side by side, with its source and tier
Scope note what this record leaves to other records
Not this deal — carried elsewhere or not carried: Vineyard Wind v. GE Renewables (every figure is one plaintiff's complaint read eight times; GEV's own offshore-wind contract losses $379M/$1,005M/$637M 2023–25 are a 10-K disclosure, not the claim amount); the Prolec GE buyout ($5.275B announced / $5,254M cash / $4.9B net — three stages, not a dispute; the CEO's 'almost $3 billion' at Bernstein is a misspeak that passes citation-verification); BWRX-300 / Darlington costs (CAD 6.1B vs 7.7B 'including common infrastructure'; no vendor primary); the Alstom price ($16.9B vs $13.5B EV — one IEEFA document contradicting itself); headcount (~75,000 10-K boilerplate for both 2024 and 2025 vs 79,199 pay-ratio population vs ~85,000 post-Prolec boilerplate); GE's 2020 SEC penalty ($200M, respondent is GE not GEV); the 'meta' topic bucket (41 claims, no Meta agreement in any of them); Fermi's TM2500 lease prepayment and NRG's TEF loans (counterparties' own balance sheets); Crusoe's 29 LM2500XPRESS units / ~1 GW (an order, not a reservation — Abilene, see sg-crusoe-jv). Adjacent facts that ARE sourced: ~60% of the 50 GW on contract was U.S. at 1Q25 (call); Electrification (grid) equipment orders for data centers $2.4B in 1Q26 and >$5B YTD at 2Q26, 'more than double our 2025 total' (releases) — the transformer side of the same chokepoint, not in the GW series; 'One turbine can cost more than $250 million, according to industry estimates' (CNBC) has no attributable estimator and is not carried. Two corrections: production is ~12–15 GW/yr shipped (not ~10) with 20 GW/yr a 3Q26 target, and the surge was 83 → 100 → 116, with almost all the new contracts reservations (19 of the 21 GW signed in 1Q26, 18 of the 20 in 2Q26); in 3Q26 (122) the reservation total fell for the first time in the series (63 → 58), because 13 GW of holds converted to orders against 8 GW of new ones.