Firebird–Kazakhstan

Firebird, a US AI-cloud startup, says it holds a US export licence for 45,000 Nvidia Grace Blackwell GPUs for a first data center in Kazakhstan that state-owned Kazakhtelecom is building for it to lease, aiming to open in the third quarter of 2027; it says a planned second phase could bring its potential capacity in Kazakhstan to about 500 , though its own website still gives the site 250 MW. Firebird's own investment is put at $3.5B to $5B, and no rent, chip price or customer is public.

A deal between Firebird, Kazakhtelecom, Nvidia, US government

Why it matters

Kazakhstan is providing the land, power and a state-funded building, while Firebird is to own the chips and sell the computing. Firebird says it holds the crucial US export licence. Kazakhstan's AI minister says the country received the authorization, and no licence text is public.

Tap a figure for the line in its source.

US government gives Firebird

  • Nvidia Grace Blackwell GPUs a US export licence covers for the first phase, as Firebird and Nvidia state it — the landlord's earlier post says 'more than 44,000', Kazakhstan's AI minister speaks of the country as the holder, and the licence itself is not public; about 65,000 more GPUs are applied for

Nvidia gives Firebird

  • GB300 GPUs the first phase is to deploy, with Nvidia helping design the cluster — bought and owned by Firebird; no price, order or server maker on file

Kazakhtelecom gives Firebird

  • disputeda data center at Data Center Valley in Ekibastuz, designed, built and handed over by KT-Telecom — Kazakhtelecom's venture with Samruk-Kazyna Invest — under a build-to-suit agreement of Oct 2 2026, then leased to Firebird's Kazakh subsidiary long-term; the documents give 100–125 (Firebird's CEO), 125, 109, 136 and 164

Firebird gives Kazakhtelecom

  • rent under the long-term lease that follows handover — no amount, term or start date in any document

Jun 15, 2026 announced by Kazakhstan's AI ministry and Firebird at the Astana signingupdated Nov 18, 2026under construction disclosed by the parties

What happened

Firebird, a San Francisco start-up, rents out computing on Nvidia chips. It signed agreements in Astana in June 2026 with Kazakhstan's AI ministry and Kazakhtelecom, the state-controlled telecom company. Firebird opened its first data center in Armenia in August 2026. In October, Kazakhtelecom's data center venture began building Firebird's first site at Data Center Valley, a state campus in Ekibastuz. The venture plans to hand over the site and lease it to Firebird. Firebird aims to open in the third quarter of 2027. Kazakhstan's government put the June package at $10 billion. Others describe that figure as potential, with no binding investment. The Kazakh side pays for the buildings, power and cooling. Firebird is to buy and own the chips and find customers. Firebird puts its investment at $5 billion. A regional government heard $3.5 billion. Firebird said it held a US export licence for 45,000 Nvidia Grace Blackwell GPUs, or graphics processing units, for the site. Firebird said a planned second phase could bring its potential capacity in Kazakhstan to about 500 . Its own website still gives the site 250 MW. Figures for the building's size range from 100 to 164 MW. No rent, chip price, customer or licence text is public. Firebird's pledge of computing for Kazakh users changed from “up to 10%” in June to “at least 10%” in October. The ministry says none is set aside yet.

Sources 32 documents — 8 other documents · 7 government statements · 7 company releases · 5 social posts · 4 press reports · 1 law-firm note

Research trail Found 132 documents and read 126 of them while checking this deal and related ones.

  1. Kazakhstan (government) · government statementgov.kz
    States 2 figures: june agreements · customers
  2. company releasefirebird.ai
    States licence
  3. company releasefirebird.ai
    States licence first public
  4. company releasefirebird.ai
    States licence conditions
  5. law-firm note (archived copy)dentons.com
    States build to suit
  6. cdn.financialreports.eu · other documentcdn.financialreports.eu
    States 50% builder
  7. Kazakhstan's prime minister · government statementprimeminister.kz
    States 70% construction
  8. Times of Central Asia · press report (archived copy)timesca.com
    States more applied
  9. Taipei Times · press reportJun 16, 2026taipeitimes.com
    States roles
  10. company releaseblogs.nvidia.com
    States investment agreement
  11. company releasefirebird.ai
    Cited by the record; no single figure is quoted from it.
  12. company releasefirebird.ai
    Cited by the record; no single figure is quoted from it.
  13. company releasefirebird.ai
    Cited by the record; no single figure is quoted from it.
  14. social postlinkedin.com
    Cited by the record; no single figure is quoted from it.
  15. government statementgov.kz
    Cited by the record; no single figure is quoted from it.
  16. government statementprimeminister.kz
    Cited by the record; no single figure is quoted from it.
  17. government statementprimeminister.kz
    Cited by the record; no single figure is quoted from it.
  18. government statementgov.kz
    Cited by the record; no single figure is quoted from it.
  19. other documentt.me
    Cited by the record; no single figure is quoted from it.
  20. government statementakorda.kz
    Cited by the record; no single figure is quoted from it.
  21. social postlinkedin.com
    Cited by the record; no single figure is quoted from it.
  22. social postlinkedin.com
    Cited by the record; no single figure is quoted from it.
  23. social postlinkedin.com
    Cited by the record; no single figure is quoted from it.
  24. social postlinkedin.com
    Cited by the record; no single figure is quoted from it.
  25. other documentadaggroup.com
    Cited by the record; no single figure is quoted from it.
  26. other documentforbes.kz
    Cited by the record; no single figure is quoted from it.
  27. other documentc14news.com
    Cited by the record; no single figure is quoted from it.
  28. press reporttimesca.com
    Cited by the record; no single figure is quoted from it.
  29. press reporttimesca.com
    Cited by the record; no single figure is quoted from it.
  30. other documentbes.media
    Cited by the record; no single figure is quoted from it.
  31. other documentcaspianpolicy.org
    Cited by the record; no single figure is quoted from it.
  32. other documentJun 15, 2026ru.themoscowtimes.com
    Cited by the record; no single figure is quoted from it.

The record's own summary of its sourcing: Firebird releases (Oct 23 + Aug 8 2026), compliance, data-centers and home pages, June LinkedIn post; Nvidia blog (Oct 22 2026); Kazakhstan AI ministry (Jun 15 + Oct 19 2026), Prime Minister's office (Oct 6 + Nov 6 2026), Pavlodar akimat (Oct 14 2026), government Telegram (Jun 26 2026) and President's office (Oct 23 2026); Dentons (Oct 6 2026, Wayback); Data Center Valley posts (Jun + Oct 2026); Kazakhtelecom H1 2026 interim statements; Adag Group; Bloomberg via Taipei Times, Reuters via The Moscow Times, The Times of Central Asia, C14, BES.media, Caspian Policy Center (read 2026-11) · as of Nov 2026

The evidence 11 sourced figures · 9 disputes

The record's headline Firebird–Kazakhstan: a US export licence for 45,000 Nvidia Grace Blackwell GPUs (Firebird, Oct 23 2026) for a first data center that state-owned Kazakhtelecom is building at Data Center Valley to hand over and lease to Firebird — launch targeted Q3 2027, ~500 'potential' after a planned second phase; its size (100–164 MW) and Firebird's investment ($3.5–5B) differ from document to document, and no rent, chip price, customer or licence text is on file

Size
45,000 Grace Blackwell GPUs licensed for phase 1, as Firebird states it ('more than 44,000' to 'more than 45,000' across five statements) · first phase 100–164 MW (100–125 from Firebird's CEO, 125, 109, 136 and 164 MW in the documents) · Firebird's investment $3.5–5B, and whether the state's ~$1B is inside it unsettled · ~500 MW 'potential' in Kazakhstan after a planned phase 2 · no rent, chip price, customer or licence text disclosed
When
Apr 29 2026 Firebird and Nvidia meet President Tokayev → Jun 15 2026 agreements signed in Astana ('totaling $10 billion', the ministry) → Aug 8 2026 Firebird: 125 MW secured at Data Center Valley, with BIS export authorization → Oct 2 2026 build-to-suit agreement signed; construction officially begins → Oct 13 2026 the AI minister: authorization for 45,000 GB300 received, ~65,000 more applied for → Oct 22–23 2026 Nvidia's blog and Firebird's release: licence for 45,000 Grace Blackwell GPUs, launch in Q3 2027, ~500 MW after a planned phase 2 → Nov 6 2026 pit excavation 70% complete → Q3 2027 launch target
Status
under construction — pit excavation for the Firebird building 70% complete on Nov 6 2026; launch targeted for Q3 2027 (Firebird, the Prime Minister's office); the government had earlier said mid-2027 for its first 125 MW. US export licence secured for phase 1 (Firebird, Oct 23 2026; a BIS authorization for Kazakhstan first mentioned, without a count, on Aug 8 2026); about 65,000 more GPUs applied for (the AI minister, Oct 2026). Phase 2 'planned', its size and timing unsettled. No customer named; the ministry says no capacity is yet set aside for Kazakh users
Structure
a state-built facility leased to a private licensee: a June 15 2026 package — a Strategic Cooperation Agreement between Kazakhstan's Ministry of Artificial Intelligence and Digital Development and Firebird (a framework, with Firebird Labs Kazakhstan at Alem.ai) and a 'Binding Term Sheet' between Kazakhtelecom and Firebird on the 'technical and organizational parameters' of the Data Center Valley project; then, on Oct 2 2026, an initial agreement among Kazakhtelecom, KT-Telecom (its venture with Samruk-Kazyna Invest, 50% each) and Firebird AI KZ Ltd. — a build-to-suit agreement under which the facility is designed, built, tested and handed over, and the framework for its long-term lease to Firebird AI KZ. The Kazakh side pays for the buildings, power, cooling and connectivity; Firebird finances, buys and owns the servers and GPUs and brings the customers; Nvidia helps design the cluster and supplies the GPUs. The chips go in under a US BIS export licence that Firebird says it secured; on Firebird's account its conditions govern who may use the computing and how users are screened and monitored. An 'investment agreement with the government of Kazakhstan' was marked at a ceremony at the presidential palace during Jensen Huang's October 2026 visit (Nvidia's blog); no text, value or date of it is public
Parties
Firebird licensee and tenant — Firebird Inc. through Firebird AI KZ Ltd., its Kazakh subsidiary; says it secured the export licence; finances, buys and owns the GPUs and servers; leases the building long-term; finds the customers · Kazakhtelecom builder-landlord — through KT-Telecom LLP, its 50/50 venture with Samruk-Kazyna Invest, which designs, builds and hands over the facility under the build-to-suit agreement and pays for buildings, power, cooling and connectivity; Kazakhtelecom itself signed the June term sheet and the October agreement · Nvidia supplier and design partner — 'supporting Firebird with the design of the project and with GPUs and other technology' (the ministry, via Bloomberg); said in Aug 2026, by Firebird's account, to intend to invest in Firebird · US government licensor (Commerce's BIS) — no licence text, date or Kazakhstan-specific condition is public
Record
disclosed / primary source · as of Nov 2026

Flows 3 as the record states them

  • Kazakhtelecom → Firebirdbuild-to-suitFirebird's first data center at Data Center Valley, Ekibastuz — designed, built, tested and handed over by KT-Telecom under the Oct 2 2026 build-to-suit agreement, then leased to Firebird AI KZ long-term; 100–164 MW across the documents (phase1-capacity). The Kazakh side pays for the buildings, power, cooling and connectivity (roles); what that costs it, and whether the ~$1B the ministry put on Kazakhtelecom in June is that cost, no document says
  • Firebird → Kazakhtelecomleaserent under the long-term lease that follows handover — no rent, term, take-or-pay or start date in any document on file
  • Firebird → Nvidiachip-spendmore than 45,000 GB300 GPUs for the first phase, which Firebird is to buy and own (roles) — no price, order, schedule or server maker named for Kazakhstan (Firebird's Armenian factory runs on Dell servers). Firebird's own estimated investment in the phase, $3.5–5B (phase1-investment), is not a price for the chips

Resolved figures 11 each with the verbatim line from its document

  • licence45,000
    Firebird's statement: a US export licence for 45,000 NVIDIA Grace Blackwell GPUs 'for the first phase of its Kazakhstan AI Factory' (release dated Oct 23 2026, posted Oct 24; its headline: 'Firebird Secures 45,000 NVIDIA Grace Blackwell GPUs'). The same release says the phase will deploy 'more than 45,000 NVIDIA GB300 GPUs'. Nvidia's blog (dated Oct 22 2026) says the same 45,000 'Grace Blackwell GPUs'. No BIS document is on file: the licence's own count, holder, date and conditions are unseen, and the other statements of them differ (licence-holder)
    “Firebird today announced that it has secured a U.S. export license for 45,000 NVIDIA Grace Blackwell GPUs for the first phase of its Kazakhstan AI Factory.”
    Firebird release (Oct 23 2026) · firebird.ai
  • licence-first-public
    the licence was public before its count: Firebird's Aug 8 2026 release, on the opening of its Armenian factory, already named an export authorization from BIS for Kazakhstan, without a GPU count, beside '125 megawatts' secured at Data Center Valley (a size now contested, phase1-capacity). The count followed in October: 'more than 44,000' in Data Center Valley's post on the Oct 2 agreement, 45,000 GB300 from the AI minister on Oct 13 (licence-holder), then Firebird and Nvidia on Oct 22–23
    “Kazakhstan has become the company's second market, where Firebird has secured 125 megawatts of AI infrastructure capacity at Data Center Valley, supported by the necessary approvals from the Government of Kazakhstan and export authorization from the U.S. Department of Commerce's Bureau of Industry and Security (BIS).”
    Firebird release (Aug 8 2026) · firebird.ai
  • licence-conditions
    what Firebird says the licence does, company-wide (its compliance page, not specific to Kazakhstan): it operates under a BIS 'export and re-export license covering our GPU deployments', whose 'Three binding conditions' govern who may be a customer or end user, how workloads are secured and monitored, and how end users are screened and reported on; every customer is screened against restricted-party lists before access. The conditions' text is not published
    “We operate under a US Bureau of Industry and Security (BIS) export and re-export license covering our GPU deployments, with additional capacity authorizations in process.”
    Firebird, 'Compliance & Export Authorization' page (2026) · firebird.ai
  • more-applied65,000
    about 65,000 more GPUs applied for, not licensed: the AI minister, Zhaslan Madiyev, to The Times of Central Asia (Oct 13 2026), and to C14 — 'we secured more than 45,000 GB300 GPUs and applied for another 65,000 Vera Rubins'. One speaker in two interviews; no BIS document
    “Madiyev said Kazakhstan has received United States Bureau of Industry and Security authorization covering 45,000 NVIDIA GB300 Blackwell Ultra graphics processing units (GPUs) and is applying for authorization for approximately 65,000 additional latest-generation GPUs.”
    The Times of Central Asia, interview with Madiyev (Oct 13 2026, Wayback) · web.archive.org
  • june-agreements
    what was signed on Jun 15 2026 in Astana, by the ministry's own account: a Strategic Cooperation Agreement between the Ministry of AI and Digital Development and Firebird — 'a framework for AI ecosystem development and the creation of Firebird Labs Kazakhstan at Alem.ai' — and a Binding Term Sheet between Kazakhtelecom and Firebird. Neither text is public; what the '$10 billion' put on them means is contested (package-value)
    “A Binding Term Sheet between JSC Kazakhtelecom and Firebird outlining the technical and organizational parameters of cooperation within the Data Center Valley project.”
    Kazakhstan AI ministry release (Jun 15 2026) · gov.kz
  • build-to-suit
    the contract: 'Kazakhtelecom, KT-Telecom and Firebird AI KZ signed an initial agreement on October 2, 2026', which 'marked the official commencement of construction'; Dentons, Firebird AI KZ's counsel, structured and negotiated 'a build-to-suit agreement' (release of Oct 6 2026). Data Center Valley's post on the signing calls it an agreement 'to build a 136 MW data center' (phase1-capacity). No rent, term, take-or-pay or handover date is public. A counsel's release about its own client's deal, read from the Wayback copy
    “This agreement governs the design, construction, testing and handover of the data center facility and establishes the contractual framework for its subsequent long-term lease to Firebird AI KZ Ltd.”
    Dentons release (Oct 6 2026, Wayback) · web.archive.org
  • roles
    who pays for what, on the ministry's account: Firebird's Kazakh subsidiary secures and finances the computing; Kazakhtelecom provides power, cooling and connectivity; 'Nvidia is supporting Firebird with the design of the project and with GPUs and other technology' (Bloomberg, Jun 16 2026). The ministry's answers to BES.media (Oct 20 2026) say the same in more detail: KT-Telecom pays for the buildings, power supply, cooling and other engineering; Firebird pays for the servers, GPUs and other computing equipment, which will belong to it, and brings in the international customers; Nvidia helps design the complex and supplies its GPUs; the Kazakh side contracts with Firebird directly. The Caspian Policy Center: Firebird 'will finance the AI infrastructure, including the purchase of NVIDIA chips'. How Firebird raises the money is in no document
    “Under the framework of the partnership, Firebird’s Kazakh subsidiary is to secure and finance AI computing infrastructure and related technology, while Kazakhtelecom is to be responsible for the power, cooling and telecommunications connectivity needed for data centers.”
    Bloomberg via Taipei Times (Jun 16 2026); BES.media (Oct 20 2026) · taipeitimes.com
  • builder50%
    the builder is half state fund: KT-Telecom LLP, 'implementing the “Data Centre Valley” project', was Kazakhtelecom's wholly owned subsidiary until it disposed of 50% on Mar 16 2026; the other 50% is held by Samruk-Kazyna Invest, and Kazakhtelecom accounts for KT-Telecom as a joint venture. Samruk-Kazyna, the state fund, held 89.5% of Kazakhtelecom at Jun 30 2026 (79.2% at Dec 31 2025). So the landlord is state-owned on both sides
    “The remaining 50% interest in KT-Telecom LLP is held by Samruk-Kazyna Invest LLP.”
    Kazakhtelecom interim condensed consolidated financial statements, H1 2026 (unaudited), Note 7 · cdn.financialreports.eu
  • construction70%
    progress at Nov 6 2026, by Kazakhtelecom's chairman to the Prime Minister: the Firebird building — the campus's second data center, named 'Firebird AI' — had its pit excavation 70% complete; the first, 68 MW building — not Firebird's: the AI minister expects it to run as a Kazakhtelecom data center for several tenants — had moved to foundations. The 164 MW the release gives the Firebird building is one of five sizes (phase1-capacity)
    “In parallel, work is underway to create the second data center, Firebird AI, with a capacity of 164 MW. At the current stage, pit excavation is 70% complete.”
    Prime Minister's office release (Nov 6 2026) · primeminister.kz
  • investment-agreement
    the October signing: Nvidia's blog says Huang's visit 'coincided with a signing ceremony marking Firebird’s investment agreement with the government of Kazakhstan, held at the presidential palace'. No party publishes its text, value or date; the President's office's account of Huang's Oct 23 visit names 'Firebird AI KZ Ltd' and Kazakhtelecom as Nvidia's partners but describes no signing, and Firebird's release says its expansion 'builds on strategic cooperation agreements signed with the Government of Kazakhstan in June 2026'. The sentence is not in the two earliest Wayback copies of the blog (Oct 23, 03:17 and 04:47 UTC; the first has no Firebird paragraph at all) — it was added after publication
    “The visits coincided with a signing ceremony marking Firebird’s investment agreement with the government of Kazakhstan, held at the presidential palace.”
    Nvidia blog (Oct 22 2026) · blogs.nvidia.com
  • customers
    no customer is named anywhere. Kazakhtelecom's chairman said at the June signing that Firebird 'already have secured service agreements with major global players', naming none; the ministry told BES.media in October that international technology companies make up the main demand, that Firebird has agreements with large foreign customers, and that Kazakh users' requests will be considered as they come (local-share). The ministry's Oct 19 line that the first phase's 215 MW is 'fully reserved' names no one either, and 215 MW is the size of the substation acquired for the campus's power supply (the Prime Minister's office, Aug 13 2026)
    “This is a joint venture, and our partners at Firebird already have secured service agreements with major global players, which will help generate foreign currency revenues for Kazakhstan”
    Kazakhstan AI ministry release (Jun 15 2026) · gov.kz

Contested figures 30 not reconciled — every position side by side, with its source and tier

phase1-capacity5 positions, side by side
~125 MW — the ministry in June, via Bloomberg ('the 125-megawatt facility'); Firebird's Aug 8 release ('secured 125 megawatts of AI infrastructure capacity at Data Center Valley'); the Prime Minister to Parliament (Jun 26): a 125 MW center in the first half of 2027 and, in 2028, 'еще один точно такой же' (another just like it) of 125 MW; the AI minister on Oct 13: Firebird's first phase of 'approximately 125 MW'. Firebird's June post: 'a planned 125MW+ ... campus, and scaling to 250MW+' Bloomberg via Taipei Times (Jun 16 2026); Firebird release (Aug 8 2026); Times of Central Asia (Oct 13 2026) · firebird.ai
100–125 MW — Firebird's CEO, Razmig Hovaghimian, in June: 'The project volume is 5 billion US dollars for the first 100–125 MW' (Data Center Valley's post) Data Center Valley LinkedIn post (Jun 2026) · linkedin.com
up to 109 MW — Firebird's Oct 23 release: 'an AI cluster with potential capacity of up to 109 MW'; 109 MW as the first of two phases, '109 MW of power' then 136 MW, in Reuters' Jun 15 report and a Data Center Valley post; the Pavlodar akimat (Oct 14): a '109 MW' data center. The Prime Minister's office on Oct 6 dated a 109 MW tranche to Q2 2028, after 186 MW in 2027 Firebird release (Oct 23 2026); Reuters via The Moscow Times (Jun 15 2026); Pavlodar akimat (Oct 14 2026); Prime Minister's office (Oct 6 2026) · firebird.ai
136 MW — Data Center Valley's post on the Oct 2 signing: 'KT-Telecom and FireBird AI KZ signed an agreement to build a 136 MW data center in Ekibastuz'. The same channel's June post gives 136 MW as the SECOND phase (109 + 136 = 245 MW), so the contract's 136 MW may not be the first phase Data Center Valley LinkedIn post (Oct 2026) · linkedin.com
164 MW — the Prime Minister's office (Nov 6): 'the second data center, Firebird AI, with a capacity of 164 MW', one of three first-phase buildings of 68 + 164 + 72 = 304 MW, all due in 2027. Two weeks after Firebird's 'up to 109 MW'; no document reconciles them or says whether either is IT load or grid power Prime Minister's office release (Nov 6 2026) · primeminister.kz
phase1-investment4 positions, side by side
$5B, Firebird's own — its Oct 23 release: 'The project envisages Firebird’s estimated investment of $5 billion and the development of an AI cluster with potential capacity of up to 109 MW, deploying more than 45,000 NVIDIA GB300 GPUs'. Read with roles, the buildings would then be on top, paid by the Kazakh side Firebird release (Oct 23 2026) · firebird.ai
$5B in all, ~$1B of it Kazakhtelecom's — the ministry in June, via Bloomberg: 'US$5 billion in investments in phase one — including US$1 billion provided by state-run Kazakhtelecom', with 'the estimated US$5 billion in additional investments' of a second phase to be determined later; so Firebird's part would be ~$4B. Kazakhtelecom's chairman reposted it ('with Kazakhtelecom contributing $1 billion'); the ministry statement itself is not on file Bloomberg via Taipei Times (Jun 16 2026) · taipeitimes.com
$3.5 billion — the Pavlodar regional akimat (Oct 14 2026): 'Компания Firebird AI KZ также заявила о планах инвестировать 3,5 млрд долларов, в том числе в строительство дата-центра мощностью 109 МВт' (Firebird AI KZ also announced plans to invest $3.5 billion, including in building a 109 MW data center) — nine days before Firebird's own $5B Pavlodar akimat release (Oct 14 2026) · gov.kz
$5B as 'the total investment in the project' — Data Center Valley's post on the Oct 2 signing, beside the 136 MW: the same number as the project's whole cost, not Firebird's share Data Center Valley LinkedIn post (Oct 2026) · linkedin.com
package-value5 positions, side by side
$10B, signed — the ministry (Jun 15): 'agreements on artificial intelligence and digital infrastructure cooperation totaling $10 billion were signed'; 'The planned $10 billion investment' is to build a cluster of '100,000 state-of-the-art GPU chips, including NVIDIA GB300 and Vera Rubin'. The Prime Minister to Parliament (Jun 26): investment under consideration of 'порядка $10 млрд' (about $10 billion) Kazakhstan AI ministry release (Jun 15 2026); government Telegram (Jun 26 2026) · gov.kz
up to $10B, potential — Bloomberg: accords 'that could bring as much as US$10 billion in investment'; Dentons, Firebird AI KZ's own counsel: agreements 'with a stated potential investment value of up to US$10 billion' Bloomberg via Taipei Times (Jun 16 2026); Dentons (Oct 6 2026) · web.archive.org
no binding investment — the Caspian Policy Center: 'The project in Kazakhstan is valued at $10 billion, but the Astana agreements included no binding investment'; The Times of Central Asia (Oct 2026): 'For now, the $10 billion represents the announced value of the agreements' Caspian Policy Center (2026); Times of Central Asia (Oct 2026) · caspianpolicy.org
more than $10B, already attracted — the Prime Minister to the President, as reported by The Times of Central Asia (Jul 2026): 'He said the project had attracted more than $10 billion in foreign investment' Times of Central Asia (Jul 2026) · timesca.com
~$10B and ~$5B in one release — the ministry's Oct 19 site-visit release gives the project's expected total investment as 'порядка 10 млрд долларов' (about $10 billion) in one paragraph and 'порядка 5 млрд долларов США' (about $5 billion) in another. Forbes Kazakhstan reported the $5B as a halving, then added that the ministry's press office had corrected the release 'с $5 млрд до $10 млрд' (from $5 billion to $10 billion); no explanation was given Kazakhstan AI ministry release (Oct 19 2026); Forbes Kazakhstan (Oct 2026) · gov.kz
total-capacity4 positions, side by side
~500 MW in Kazakhstan — Firebird's Oct 23 release: 'A planned second phase would bring Firebird’s total potential AI infrastructure capacity in Kazakhstan to approximately 500 MW'; Nvidia's blog the same. 'Potential', after a phase that is 'planned', of which no size or date is given Firebird release (Oct 23 2026); Nvidia blog (Oct 22 2026) · firebird.ai
~250 MW — Firebird's June post ('beginning with a planned 125MW+ next-generation AI data center campus, and scaling to 250MW+'); its own data-centers page, still: the Kazakhstan site, DC-3, marked 'Planned', at '75K NVIDIA GB300' and 250 MW — 'a 75,000-GPU site in Kazakhstan'; two phases of 109 + 136 = 245 MW (Reuters, Jun 15; Data Center Valley); the Prime Minister: two 125 MW centers Firebird LinkedIn post (Jun 2026) and data-centers page; Reuters via The Moscow Times (Jun 15 2026) · firebird.ai
500 MW across Armenia and Kazakhstan together — Firebird's homepage: 'We’re starting with our 500MW flagship AI supercomputers in Armenia and Kazakhstan and scaling to 2.5GW worldwide by 2028'; Adag Group, its construction-management contractor: the initiative across both countries 'is designed to scale beyond 500MW of IT capacity and support up to 100,000 GPUs'. Armenia alone is planned at 300 MW by end-2027 (Firebird, Aug 8), so the two readings differ by about that much Firebird homepage (2026); Adag Group (2026) · adaggroup.com
a share of 480 MW, up to 620 MW — the Prime Minister's office (Nov 6): for the campus's second phase, 'preliminary agreements have been signed with Gaw Capital, Boosteroid, and Firebird to locate 480 MW of computing capacity, with the possibility of expansion up to 620 MW'; no split among the three Prime Minister's office release (Nov 6 2026) · primeminister.kz
later-chips2 positions, side by side
Grace Blackwell (GB300) — the licence and the first phase (licence); Firebird's data-centers page gives the Kazakhstan site as '75K NVIDIA GB300' Firebird release (Oct 23 2026) and data-centers page · firebird.ai
Vera Rubin — Huang in Firebird's own release: 'Firebird’s expansion of NVIDIA Vera Rubin will support Kazakhstan’s researchers'; Firebird's homepage gives DC-3 — the site its data-centers page labels Kazakhstan — as 'A planned 75,000-GPU NVIDIA VR200 site across 125 MW'; the ~65,000 GPUs applied for are 'Vera Rubins' (more-applied); the ministry: 'GB300 and Vera Rubin' Firebird release (Oct 23 2026) and homepage; C14 · firebird.ai
licence-holder3 positions, side by side
Firebird holds it, 45,000 GPUs — Firebird's release and Nvidia's blog: Firebird 'has secured a U.S. export license for 45,000 NVIDIA Grace Blackwell GPUs' (licence) Firebird release (Oct 23 2026); Nvidia blog (Oct 22 2026) · firebird.ai
'more than 44,000' — Data Center Valley's post on the Oct 2 signing: 'US export licenses for the supply of more than 44,000 GPUs have already been secured for the first phase' — licences, plural, holder unnamed Data Center Valley LinkedIn post (Oct 2026) · linkedin.com
Kazakhstan, 45,000 or 'more than 45,000' GB300 — the AI minister: 'Kazakhstan has received United States Bureau of Industry and Security authorization covering 45,000 NVIDIA GB300' (The Times of Central Asia's paraphrase, Oct 13); to C14: 'We applied for the export license, we secured more than 45,000 GB300 GPUs' Times of Central Asia (Oct 13 2026, Wayback); C14 · c14news.com
launch2 positions, side by side
the third quarter of 2027 — Firebird's release: 'Phase 1 is targeting commercial launch in Q3 2027'; Nvidia's blog: 'targeting commercial launch in the third quarter of 2027'; the Prime Minister's office (Nov 6), of the Firebird AI building: 'The completion of works and launch are scheduled for the third quarter of 2027'; the AI minister (Oct 13): Firebird's first phase completed 'in the third quarter of 2027' Firebird release (Oct 23 2026); Prime Minister's office (Nov 6 2026) · primeminister.kz
the first half of 2027 — the government in June: commercial operations at 'the 125-megawatt facility planned to start next year' (the ministry via Bloomberg); the Prime Minister to Parliament (Jun 26): 'в первом полугодии следующего года запустим ЦОД мощностью 125 МВт' (in the first half of next year we will launch a 125 MW data center). Since August the government dates the campus's first building — 50, then 68 MW, not Firebird's: the AI minister expects Kazakhtelecom to run it for several tenants — to June / Q2 2027 (the Prime Minister's office, Aug 13 and Nov 6); no document says whether the June date moved or meant another building Bloomberg via Taipei Times (Jun 16 2026); government Telegram (Jun 26 2026); Prime Minister's office (Aug 13 2026) · t.me
local-share3 positions, side by side
up to 10%, explored — Firebird's June post: 'Exploration of reserving up to 10% of compute capacity for Kazakhstan-based companies and government entities' Firebird LinkedIn post (Jun 2026) · linkedin.com
at least 10%, committed — Firebird's Oct 23 release: 'Firebird is committed to allocating at least 10% of total GPU capacity to Kazakhstani companies and government agencies' Firebird release (Oct 23 2026) · firebird.ai
none set aside yet, and paid — the ministry to BES.media (Oct 20): 'Отдельную долю мощностей для Казахстана пока не выделили' (no separate share of capacity has yet been allocated for Kazakhstan); Kazakh users will pay, tariffs are not set, and access and volumes will be decided closer to launch BES.media (Oct 20 2026) · bes.media
nvidia-investment2 positions, side by side
intends to invest — Firebird (Aug 8 2026): 'Firebird also announced that NVIDIA intends to invest in the company, following an earlier investment by CoreWeave this year'; no amount for either. Nvidia also supplies the GPUs (roles) Firebird release (Aug 8 2026) · firebird.ai
nothing secured — the Caspian Policy Center, of Firebird's Armenian phase two: 'The remainder of the $4 billion cost remains unfinanced, with no outside investment yet secured from U.S. partners or NVIDIA'. Intent and nothing yet secured can both be true; no document shows Nvidia money in Firebird Caspian Policy Center (2026) · caspianpolicy.org

Scope note what this record leaves to other records

NOT this record (carried on the entities or not carried): the Data Center Valley campus as a whole — its 1 GW target (3 GW 'very optimistic', 5 GW attributed to Huang), the 68 MW and 72 MW buildings that are not Firebird's, 304 vs 295 MW phase-one schedules, the 215 MW substation and 'fully reserved' claim, 300 MW 'available', land (124.4 to 1,400 ha), the ~2.5 US cents/kWh power price on offer and the four-year GRES-1 supply contract, take-or-pay talk, ~$30B / $115B campus investment figures, $3–3.1B a year of export revenue and the jobs counts; KT-Telecom's financing (a USD 1,207,129,000 bond programme with USD 41.5M and 71.0M tranches, a KZT 16.24bn group loan, and GEOBOX's tier-3 DBK loan, yuan bonds, subsidy and contract chain), its H1 loss (KZT 308.3m filed vs 395.9m GEOBOX) and Samruk-Kazyna's 748.0bn-tenge cost line; Kazakhstan's power balance; Kazakhtelecom's own GPUs (400 H200 + 480 B300, >1,000 + >1,000 Vera Rubin planned) → the kazakhtelecom entity; other tenants (Energy Capital Global, China Energy, Gaw Capital, Boosteroid) and other projects (Freedom's $2B hub, JMOT04); Firebird's Armenia (6,144 B200, 15 vs 18 MW, $500M / $300M / $60M financing, 41,000-GPU licence, $4B phase 2), its 2 vs 2.5 GW global pipeline and website totals → the firebird entity, or not carried here. Not adopted: a 30,896-GPU 2027 Kazakhstan count is a model's MW-proportional scenario, not a fact; w.media's rewrite of the Oct 23 release drops 'Firebird’s' from the $5B, 'in Kazakhstan' from the 500 MW, and turns 'at least 10%' into 'As much as 10 percent'; ts2.tech's '51 times' is 45,000 ÷ Kazakhtelecom's 880 GPUs. Premise corrections: one reading dates the licence to Nvidia's Oct 22 post, but Firebird named a BIS authorization for Kazakhstan on Aug 8 and the 45,000 count was public by Oct 13 (licence-first-public); no Kazakhtelecom release is on file, but the documents include Firebird's own release (Oct 23), the ministry's and the Prime Minister's releases, and Data Center Valley's posts; the 'investment agreement' of Nvidia's post has no text or value anywhere (investment-agreement).

More between these companies

  1. Nov 21, 2025 updated Nov 19

Everything between Nvidia and US government →