Why it matters
Microsoft is partnering with a developer that builds its own power plant on site. Crusoe says the campus will run entirely on that plant and batteries, which it pays for; the landowner's CEO has called the gas backup. Neither company has said how much of the 900 campus is Microsoft's, for how long or at what price.
Tap a figure for the line in its source.
Crusoe gives Microsoft
- AI campus, Crusoe's measure of the site: two new buildings and an on-site power plant, on land Lancium owns next to the Stargate campus; how much of it is Microsoft's neither company says
- of critical IT load per building, as designed; the first building expected to be energized in mid-2027
- power from an on-site plant with battery storage, which Crusoe says it builds and pays for; whether the plant is the campus's main supply or its backup, Crusoe and the landowner's CEO describe differently
Microsoft gives Crusoe
- what Microsoft gives Crusoe for the campus is not disclosed; the landowner's CEO said in April that Microsoft is a tenant there for 20 years
What happened
Crusoe announced a new AI campus in Abilene, Texas, on March 27, 2026, to support AI work for Microsoft. It is on land Lancium owns, next to the Stargate campus Crusoe is building for Oracle. Crusoe calls the site 900 . It is to have two buildings and its own power plant. Each building is designed to deliver 336 MW to the computers inside. Crusoe expects the first building to be energized in mid-2027. A Microsoft executive wrote that Microsoft is partnering with Crusoe on the campus. Neither company has said how much of the campus is Microsoft's, what it pays or for how long. Lancium's chief executive said in April that Microsoft is a tenant for 20 years, in buildings 9 and 10. On March 24, Bloomberg, citing unnamed people, reported that Microsoft had agreed to rent the site, which it put at roughly 700 MW. After Crusoe's announcement, it said 900 MW. Crusoe says the campus will run entirely on its own power plant and batteries, which it builds and pays for. Lancium's chief executive described the gas generation for buildings 9 and 10 as backup for reliability. Crusoe gives its on-site plant as 900 MW. A draft state air permit for a gas plant for buildings 9 and 10 puts it at about 1,330 MW. No document says whether these are the same plant. Four Texas building filings, two for each building, each list an estimated cost of $6.3 billion. They do not say whether those figures add up. Press reports, citing unnamed people, say the site was first meant for Oracle and OpenAI, which walked away from it. Crusoe calls the campus new and does not mention them.
Sources 24 documents — 7 government statements · 6 other documents · 4 company releases · 4 press reports · 1 social post · 1 SEC filing · 1 research note
- States 4 figures: 900 MW site capacity · 336 MW IT load · first energization · 2.1 GW site total (for context)
- States 900 MW ground broken
- States 900 MW land
- States msft confirms
- States 336 MW buildings
- States registrations
- States permit buildings
- States $364.6B msft filings (for context)
- States 900 MW gas supply (for context)
- States lease term
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
- Cited by the record; no single figure is quoted from it.
The record's own summary of its sourcing: Crusoe releases (Mar 27, Jun 9, Jul 15 with Lancium, Aug 8 2026); Noelle Walsh's LinkedIn post and Microsoft's Q1 FY2027 10-Q; TDLR registrations, the City of Abilene's site plan and TCEQ's permit 182126 papers; KTXS and the West Texas Tribune for Lancium's CEO; Bloomberg, Reuters, DCD, GridLeads and Epoch AI for the contested cells; Energy Transfer's decks for context (read 2026-11) · as of Nov 2026
The evidence 10 sourced figures · 5 disputes · 3 for context
The record's headline Crusoe–Microsoft: a 900 AI campus in Abilene, Texas — two buildings designed for 336 MW of IT load each and an on-site power plant, beside the Stargate campus (Mar 27 2026); first building expected energized mid-2027, with no size for Microsoft's share, term, price or financing from either company
- Size
- 900 MW site (Crusoe's measure) · two buildings designed for 336 MW of critical IT load each · Microsoft's share contested (about 700 or 900 MW in Bloomberg's reports) · 20 years by the landowner's CEO · no rent, value or financing disclosed
- When
- Nov 7 2025 (air-permit application for the plant) → Dec 17 2025 (Buildings 9 and 10 registered with Texas) → Mar 24 2026 (Bloomberg reports Microsoft will rent the site) → Mar 27 2026 (Crusoe announces the campus; Microsoft's Noelle Walsh posts) → by Jun 9 2026 (ground broken) → Aug 2026 (TCEQ's draft decision on the permit) → mid-2027 (first building expected energized) → Nov 11 2027 (Building 10's registered fit-out completion)
- Status
- under construction: Crusoe 'recently broke ground' (Jun 9 2026); Texas's registrations (Dec 2025) planned the shells from Feb–Mar 2026 and the fit-outs to finish Sep 17 and Nov 11 2027; the air permits for a gas plant for Buildings 9 and 10 still pending at TCEQ on Nov 21 2026, after its Aug 2026 draft decision; the first building expected energized in mid-2027
- Structure
- a campus Crusoe develops for Microsoft on land Lancium owns, adjacent to the Stargate Abilene campus: two data-center buildings — Buildings 9 and 10, by Lancium's CEO and the site plan filed with the city, which marks Building 10 '336 MW DATA CENTER'; Texas registered them with Abilene DC9, LLC and Abilene DC10, LLC as owners, whose own owners no document on file names — and an on-site power plant with battery storage, which Crusoe calls behind-the-meter and says it builds and pays for (Lancium's CEO calls the gas backup: power-source). Crusoe counts the campus in a development portfolio it calls 'contracted to hyperscale clients' (Jun 9 2026); Microsoft's word is 'partnering'. No lease, rent, schedule, financing or guarantee is public
- Programme
- Microsoft–Crusoe
- Parties
- Crusoe developer — builds the campus and its on-site power plant, which it says it pays for; issued the release; Crusoe Technologies LLC is the applicant TCEQ names for a gas plant for Buildings 9 and 10 (plant-capacity) · Microsoft the campus's customer ('Supporting large scale AI workloads for Microsoft'); its cloud operations president calls it a partnership; its 10-Q for the quarter to Sep 30 2026 names neither Crusoe nor Abilene
- Record
- disclosed / primary source · as of Nov 2026
Flows 2 as the record states them
- Crusoe → Microsoftcapacitya campus of two buildings, each designed for 336 MW of critical IT load, on a 900 MW site with its own on-site power plant and battery storage, beside the Stargate Abilene campus; the first building expected energized in mid-2027. How much of it is Microsoft's is contested (microsoft-share)
- Microsoft → Crusoepaymentsnot disclosed — no rent, value, term or schedule in any party's document; 20 years by the landowner's CEO (lease-term). Microsoft's 10-Q for the quarter to Sep 30 2026 names neither Crusoe nor Abilene (msft-filings)
Resolved figures 10 each with the verbatim line from its document
- site-capacity900 MW900 MW — Crusoe's figure for the site, which it says supports 'large scale AI workloads for Microsoft' and holds two new buildings and an on-site power plant. Crusoe uses the same 900 MW for the plant (contested plant-capacity). It is not the IT load, 336 MW per building (it-load), and Crusoe never says how much of it is Microsoft's (contested microsoft-share). Its Jun 9 2026 update repeats it as 'a second 900 MW campus in Abilene for Microsoft' (ground-broken)
“Supporting large scale AI workloads for Microsoft, the 900 MW site includes two new buildings and an onsite power plant to support grid resilience.”
Crusoe release (Mar 27 2026) · crusoe.ai - it-load336 MW336 MW of critical IT load per building, as designed ('designed to deliver') — the power for the computers, below the site's 900 MW headline. Two buildings make 672 MW, our arithmetic: neither Crusoe nor Microsoft states the total. The city's site plan labels Building 10 '336 MW DATA CENTER' (buildings)
“Each of the two new buildings is designed to deliver 336 MW of critical IT load, supporting the rack densities required by the next generation of GPU architectures.”
Crusoe release (Mar 27 2026) · crusoe.ai - first-energization2027the first building 'expected to be energized in mid-2027' — Crusoe's forecast on Mar 27 2026, with land clearing and site preparation then under way; it gives no date for the second building. Bloomberg's Mar 27 report repeats it as Crusoe's. The fit-out completion dates in Texas's registrations, Sep 17 and Nov 11 2027 (registrations), are planned construction dates; Epoch's model gives the same two dates for its first and second buildings in service (campus-cost)
“Land clearing and site preparation for the new campus are already underway, with the first building expected to be energized in mid-2027”
Crusoe release (Mar 27 2026) · crusoe.ai - ground-broken900 MWunder construction by June 2026: Crusoe's update of Jun 9 2026 says it 'recently broke ground on a second 900 MW campus in Abilene for Microsoft', in a paragraph on the five campuses of its 'data center development portfolio contracted to hyperscale clients', beside the flagship next door 'purpose built for Oracle'. Crusoe never calls the deal a lease
“Crusoe's data center development portfolio contracted to hyperscale clients spans five AI data center campuses across the United States. At its flagship 1.2 GW Abilene, Texas campus – purpose built for Oracle - the first two buildings are operational and an additional six buildings are under construction. Crusoe recently broke ground on a second 900 MW campus in Abilene for Microsoft.”
Crusoe release (Jun 9 2026) · crusoe.ai - land900 MWon land Lancium owns, next to the flagship: 'a second 900 MW data center on adjacent Lancium-owned land in Abilene', in the release Crusoe and Lancium issued together on Jul 15 2026. No ground lease for this campus is on file
“Crusoe recently announced it is currently building a second 900 MW data center on adjacent Lancium-owned land in Abilene.”
Crusoe and Lancium release (Jul 15 2026; Crusoe's newsroom copy) · crusoe.ai - msft-confirmsMicrosoft's side, in its executive's own words: Noelle Walsh, President, Cloud Operations & Innovation, posted on LinkedIn on the day of Crusoe's release that 'Microsoft is partnering with Crusoe to develop a new datacenter campus in Abilene' — 'partnering', not 'lease'. She is also quoted in Crusoe's release, without a figure. When Bloomberg first reported the deal, a Microsoft spokesperson had 'nothing to share' (Reuters, Mar 24 2026). Microsoft's 10-Q for the quarter to Sep 30 2026 names neither Crusoe nor Abilene (msft-filings)
“Microsoft is partnering with Crusoe to develop a new datacenter campus in Abilene.”
Noelle Walsh (Microsoft), LinkedIn post (Mar 27 2026) · linkedin.com - lease-term2020 years, by the landowner's account: Lancium's CEO Michael McNamara, speaking to the Kiwanis Club of Abilene on Apr 8 2026. The West Texas Tribune reports the same speech: Microsoft 'has also joined the campus for buildings nine and 10 under what he described as a 20-year arrangement'. One remark, from a company that owns the land but is not named as a party to Microsoft's deal; neither Crusoe nor Microsoft states a term, or when the 20 years would start. Microsoft's 10-Q gives its leases not yet commenced terms of '1 year to 20 years' (msft-filings), which neither confirms nor rules it out
“Oracle is a tenant at the facility for the next 15 years, and Microsoft for 20.”
KTXS (Apr 8 2026), quoting Lancium's CEO · ktxs.com - buildings336 MWBuildings 9 and 10 of the Lancium campus: the site plan filed with the city, SP-2026-18 ('PHASE 3 BLDG 9&10', marked for review only), labels Building 10 '336 MW DATA CENTER' at 738,382 sq ft — Crusoe's per-building IT load and the footprint Texas registered (registrations). Lancium's CEO puts Microsoft in 'buildings nine and 10' (lease-term). Crusoe's releases never number the buildings
“PROPOSED BUILDING 10 PROPOSED USE: 336 MW DATA CENTER BUILDING FOOTPRINT: 738,382 SF”
City of Abilene site plan SP-2026-18 (Lancium Buildings 9 & 10) · abilenetx.gov - registrations738,382four registrations with Texas's licensing department (TDLR), all dated Dec 17 2025, before the deal was reported: a core-and-shell and a fit-out for each building at 617 FM 2404, each with its 'Owner Name'. Building 9, under Abilene DC9, LLC: shell Feb 21 2026 → Apr 15 2027, fit-out Apr 15 2026 → Sep 17 2027. Building 10, under Abilene DC10, LLC: shell Mar 11 2026 → May 3 2027, fit-out May 2 2026 → Nov 11 2027. Each is 738,382 sq ft, 'privately funded', with 'No' to whether the tenant provides the funds. The dates are the applicant's construction dates, not energization. Each also gives an estimated cost (contested campus-cost). None names Microsoft or says who owns the two LLCs
“THE PROPOSED PROJECT IS THE NINTH DATA CENTER ON THE SOUTH SIDE OF THE EXISTING DEVELOPED SITE. THE SINGLE STORY BUILDING IS APPROXIMATELY 738,382 SF”
TDLR registration TABS2026008297 (Building 9 core & shell; with -8308, -8318, -8329) · tdlr.texas.gov - permit-buildingsthe plant's air permit is for Buildings 9 and 10: TCEQ's modeling audit (Aug 2 2026) of the air-quality analysis submitted 'on behalf of Crusoe Energy Systems LLC' for permit 182126 calls it 'Permit 182126 (Buildings 9-10)'. The application went in on Nov 7 2025; the three permits (182126, PSDTX1688, GHGPSDTX263) were still pending on TCEQ's project record of Nov 21 2026, with a public hearing requested. No TCEQ document on file names a tenant. How big the plant is, is contested (plant-capacity)
“This operational condition is applied to this Permit 182126 (Buildings 9-10) as well as the existing PBR Registration No. 177262.”
TCEQ modeling audit, permit 182126 (Aug 2 2026) · records.tceq.texas.gov
Contested figures 12 not reconciled — every position side by side, with its source and tier
“The Abilene site, which accounts for roughly 700 megawatts of capacity, sits next to Oracle and OpenAI's flagship Stargate campus, the report said.”Bloomberg via Reuters (Mar 24 2026); DCD · finance.yahoo.com
“Microsoft Corp. will occupy a data center project previously earmarked for Oracle Corp. and OpenAI, scooping up 900 megawatts of capacity after the other two companies walked away from the site.”Bloomberg (Mar 27 2026) · web.archive.org
“Microsoft Corp. will occupy a data center project previously earmarked for Oracle Corp. and OpenAI, scooping up 900 megawatts of capacity after the other two companies walked away from the site.”Bloomberg (Mar 24 and 27 2026) · web.archive.org
“Crusoe, the AI factory company, today announced the development of a new, dedicated AI factory campus in Abilene, Texas.”Crusoe release (Mar 27 2026); TDLR; TCEQ · crusoe.ai
“The 900MW on-site power plant provides dedicated energy, paired with an MV BESS system, which is designed to enhance operational reliability and grid resilience.”Crusoe release (Mar 27 2026) · crusoe.ai
“Crusoe Technologies LLC (Crusoe) proposes construction of a new natural gas-fired simple cycle power plant at a site near Abilene in Taylor County, Texas. The power plant will have a nominal generation capacity of approximately 1,330 megawatts (MW). The new power plant will consist of 39 simple-cycle combustion turbines”TCEQ preliminary determination summary, permits 182126 / PSDTX1688 / GHGPSDTX263 (Aug 2026) · s3.amazonaws.com
“The new power block will consist of 41 GE Model LM2500/ Aero DT35 natural gas fueled turbines”GridLeads, quoting the TCEQ application (project 400428) · gridleads.co
“In Abilene, our new campus will run entirely on on-site generation and battery storage, built and paid for by Crusoe.”Crusoe statement (Aug 8 2026); Crusoe release (Mar 27 2026) · crusoe.ai
“Natural gas generation at the site is designated for reliability backup for buildings nine and 10 and is housed in an enclosed hollow designed to minimize noise on surrounding roads.”West Texas Tribune (May 5 2026) and KTXS (Apr 8 2026), on Lancium's CEO · westtexastribune.org
“Estimated Cost: $6,300,000,000”TDLR registrations TABS2026008297, -8308, -8318, -8329 (Dec 17 2025) · tdlr.texas.gov
For context, not this deal's figures 3 kept beside the deal so they are not mistaken for its numbers
- site-total2.1 GW2.1 GW, the whole Abilene site as Crusoe projects it: this campus's 900 MW added to the flagship's 1.2 GW (sg-crusoe-jv). A sum of two campuses on Crusoe's headline bases, not this deal's size
“The new campus is located adjacent to Crusoe's existing Abilene AI factory infrastructure, bringing the total projected capacity across the full Abilene site to 2.1 gigawatts (GW).”
Crusoe release (Mar 27 2026) · crusoe.ai - msft-filings$364.6BMicrosoft's own filings do not show the campus: its 10-Q for the quarter to Sep 30 2026 names neither Crusoe nor Abilene, and gives only the total of all its leases not yet commenced, mostly data centers — $364.6B, to commence in fiscal 2027–2034, with terms of 1 to 20 years. Whether this campus is among them is not stated
“As of September 30, 2026, we had additional leases, primarily for datacenters, that had not yet commenced of $364.6 billion, with some arrangements subject to certain contractual conditions being met.”
Microsoft 10-Q (quarter ended Sep 30 2026) · sec.gov - gas-supply900 MWthe gas for the campus's plant is another deal's: Energy Transfer says it agreed with Crusoe in the second quarter of 2026 to build facilities bringing natural gas to 'its previously announced expansion at its AI factory campus in Abilene', to 'Support ~900 MW capacity' — this campus, by our reading of the size and the word 'expansion'. Its Q3 2026 deck adds an agreement with an 'A-Rated Hyperscaler' it does not name, for 'Crusoe's previously announced AI factory campus in Abilene'; no document on file names that hyperscaler
“Entered into agreement with Crusoe to construct facilities to provide natural gas to its previously announced AI factory campus in Abilene, TX: Support ~900 MW capacity”
Energy Transfer Q2 2026 earnings presentation · energytransfer.com
Scope note what this record leaves to other records
Not this deal — carried elsewhere or not carried: the eight-building Stargate campus next door, its owners, loans and its own gas plant (sg-crusoe-jv); Oracle's contract with OpenAI and the expansion they dropped, with Bloomberg's report that Nvidia paid Crusoe a deposit and courted Meta as a tenant (sg-oai-orcl abilene-expansion), which no party connects to Microsoft's campus; Energy Transfer's gas for the campus (gas-supply, context); the City of Abilene's and Taylor County's tax abatements for Buildings 9 and 10 and the plant (a city–developer term); Crusoe's turbine orders from GE Vernova, PROENERGY, Bergen and Boom, none tied by any source to this site; the plant's permitted emissions, whose figures moved between the application and TCEQ's draft. Not adopted: a tracker's 'Microsoft formally agrees to lease 700 MW' (cutrerlabs, naming no source); EveryDataCenter's cost model, its phases to 2032 and its per-lab splits, which no party's paper describes; Stand.earth's 'Microsoft share of project capacity: 900MW' (the site figure relabelled); Tafel Power's 'Oracle (TCEQ records)' as the plant's user (no TCEQ document on file names Oracle for this permit); SAVRN's Meta as payer of the deposit (every Bloomberg-derived account names Nvidia).